New bridge over the Lima river in the Jolda interchange



CONCEPTUAL DESIGN / SERVICES CARRIED OUT

Unicellular box girder deck, in pre-stressed concrete, built by balanced cantilever method, with segments cast “in-situ”, over four piles. The side spans were constructed over soil supported formwork and connect to the central part of the deck.

LOCATION

Ponte de Lima, Portugal

SERVICE DATE

2012

GENERAL FEATURES

Length: 420 m
Main span: 130,0 m
Width: 16,10 m