New bridge over the Lima river in the Jolda interchange




CONCEPTUAL DESIGN / SERVICES CARRIED OUT
Unicellular box girder deck, in pre-stressed concrete, built by balanced cantilever method, with segments cast “in-situ”, over four piles. The side spans were constructed over soil supported formwork and connect to the central part of the deck.
LOCATION
Ponte de Lima, Portugal
SERVICE DATE
2012
GENERAL FEATURES
Length: 420 m
Main span: 130,0 m
Width: 16,10 m