Motorway connecting the Skikda Port and the Est-West Motorway



CONCEPTUAL DESIGN / SERVICES CARRIED OUT

The Detailed Design included the study of the following aspects:
• Road geometry
• Structures (viaducts, overpasses and underpasses)
• Pavement
• Geology and geotechnics
• Earthworks
• Drainage
• Retaining structures
• Signs and markings
• Guardrails
• Lighting
• Utilities
• Fences
• Land parcels design plans
• Environment and landscaping

LOCATION

Skikda, Algeria

SERVICE DATE

2017 (Predicted)

GENERAL FEATURES

• Length: 30.5 km of main road
• Cross section: 2 x 2 lanes
• 5 interchanges
• 6 roundabouts
• 6 redesigned intersected road
• 35 Structures (viaducts, overpasses and underpasses)
• Cut volume: 1 100 000 m3
• Fill volume: 8 800 000 m3